Craig Park Seawall Replacement (Phase 1)

Share Craig Park Seawall Replacement (Phase 1) on Facebook Share Craig Park Seawall Replacement (Phase 1) on Twitter Share Craig Park Seawall Replacement (Phase 1) on Linkedin Email Craig Park Seawall Replacement (Phase 1) link

**UPDATE** 6/3/2026

The boat ramp, gangway, and float dock are now OPEN! They will remain open until further notice.

Previous Updates

5/28/2026 -Beginning immediately and continuing through the remainder of the project, approved work hours will be extended from daylight hours until 10:00 PM, Monday through Saturday. Crews will continue adjusting schedules around tides. *Some days may end before10:00pm but will not exceed 10:00pm*


PURPOSE

To protect Craig Park from tidal flooding by raising the elevations around the perimeter of the park.

EXISTING CONDITIONS

  • The existing sidewalk and seawall are failing in parts around the permitter of Craig Park. Failing sidewalk sections have undergone “patch” repairs over the past few years, but they have intermittently and frequently been closed to pedestrians for safety reasons.
  • In most places the sidewalk sits at approximately +/- 2.0 feet above mean sea level.
  • The existing observation deck (the dock on the east side of Spring Bayou) sits at approximately 3.0 feet above mean sea level and is supported by a shallow sea wall. It is structurally failing and is at risk of eventual collapse.
  • A $2M grant from the Federal Government (secured through efforts of Representative Gus Bilirakis) is being used to cover a significant portion of the cost of the project. The grant covers only the waterfront adjacent to Craig Park from the boat ramp to and including the observation deck. The remaining waterfront on the north side of Spring Bayou will be completed as a later second phase.

IMPLEMENTATION

The project goal will be accomplished by the following:

  • Replacement of most of the seawall with a new seawall at a higher target elevation (5.0 feet or more above sea level)
  • Replacement of the existing sidewalk at the new elevation.
  • Replacement of the existing observation deck at the new elevation.
  • Addition of a short grassy berm (less than 2-feet above grade) around the western side of the park at the new elevation.
  • Replacement of seawall cap along the western side of the park (no seawall replacement is necessary in that portion of the project).
  • Protection of the War Memorial including additional drainage
  • Addition of drainage inlets, manatee protection grates, pipes, and stormwater check valves to prevent tidal influx throughout the park.
  • Other various repairs as needed.
  • No changes are proposed to the boat ramp or the boat ramp parking area at this time.

Events @ Craig Park- Events will NOT be affected by any construction activities.

  • Tuesday, June 23 from 10am-1pm, Playdate and Popsicles in the Park
  • Saturday July 4th from 10am-1pm, 4th of July Picnic
  • Wednesday July 22 from 11am-1pm Playdate & Popsicles in the Park


Flooded sidewalk at Spring Bayou.Flooded sidewalk along Spring Bayou.



**UPDATE** 6/3/2026

The boat ramp, gangway, and float dock are now OPEN! They will remain open until further notice.

Previous Updates

5/28/2026 -Beginning immediately and continuing through the remainder of the project, approved work hours will be extended from daylight hours until 10:00 PM, Monday through Saturday. Crews will continue adjusting schedules around tides. *Some days may end before10:00pm but will not exceed 10:00pm*


PURPOSE

To protect Craig Park from tidal flooding by raising the elevations around the perimeter of the park.

EXISTING CONDITIONS

  • The existing sidewalk and seawall are failing in parts around the permitter of Craig Park. Failing sidewalk sections have undergone “patch” repairs over the past few years, but they have intermittently and frequently been closed to pedestrians for safety reasons.
  • In most places the sidewalk sits at approximately +/- 2.0 feet above mean sea level.
  • The existing observation deck (the dock on the east side of Spring Bayou) sits at approximately 3.0 feet above mean sea level and is supported by a shallow sea wall. It is structurally failing and is at risk of eventual collapse.
  • A $2M grant from the Federal Government (secured through efforts of Representative Gus Bilirakis) is being used to cover a significant portion of the cost of the project. The grant covers only the waterfront adjacent to Craig Park from the boat ramp to and including the observation deck. The remaining waterfront on the north side of Spring Bayou will be completed as a later second phase.

IMPLEMENTATION

The project goal will be accomplished by the following:

  • Replacement of most of the seawall with a new seawall at a higher target elevation (5.0 feet or more above sea level)
  • Replacement of the existing sidewalk at the new elevation.
  • Replacement of the existing observation deck at the new elevation.
  • Addition of a short grassy berm (less than 2-feet above grade) around the western side of the park at the new elevation.
  • Replacement of seawall cap along the western side of the park (no seawall replacement is necessary in that portion of the project).
  • Protection of the War Memorial including additional drainage
  • Addition of drainage inlets, manatee protection grates, pipes, and stormwater check valves to prevent tidal influx throughout the park.
  • Other various repairs as needed.
  • No changes are proposed to the boat ramp or the boat ramp parking area at this time.

Events @ Craig Park- Events will NOT be affected by any construction activities.

  • Tuesday, June 23 from 10am-1pm, Playdate and Popsicles in the Park
  • Saturday July 4th from 10am-1pm, 4th of July Picnic
  • Wednesday July 22 from 11am-1pm Playdate & Popsicles in the Park


Flooded sidewalk at Spring Bayou.Flooded sidewalk along Spring Bayou.



Page last updated: 12 Jun 2026, 05:24 AM